FERC approved MISO’s proposed changes to its generator interconnection procedure (“GIP”) and generator interconnection agreement (“GIA”), designed to streamline MISO’s interconnection queue process. These changes will affect all interconnection requests made after January 4, 2017 and all prior requests that have not yet completed a system impact study.
The new provisions are largely designed to address delays in the Definitive Planning Phase (“DPP”) of the interconnection process caused by the need for unplanned restudies triggered when higher-queued projects leave the queue. The revised interconnection procedures contain the following changes:
- The DPP will be divided into three phases, each involving its own system impact study (Phase I – preliminary system impact study; Phase II – revised system impact study, and Phase III – final system impact study). Each phase will require a milestone payment to enter, and (following the customer’s receipt of the results of the impact study conducted during that phase), a “decision point” where the customer can withdraw from queue and receive a refund for its previous milestone payment.
- A mandatory scoping meeting (previously optional) between the interconnection customer, MISO, and the transmission owner to discuss alternative interconnection methods.
- Increased site control requirements: the interconnection customer must demonstrate 75% site control (as opposed to previous 50%) at the time of the interconnection request, and full site control at the second phase of the DPP.
- New language allowing a customer to request a Provisional GIA at any time up to and including the “decision point” in Phase II of the DPP, and (in the event of significant delays in the interconnection process) at the “decision point” in Phase III. The GIP previously did not address when a customer could make such a request.
- A new pro-forma study services agreement between MISO and any transmission owner or consultant performing interconnection studies, designating the interconnection customer as the intended beneficiary.
- Modifications to milestone payment refund provisions: a customer is entitled to a full refund of milestone payments where the cost estimates in the current DPP phase system impact study increased by more than 25% and more than $10,000 per MW over the previous phase’s study (formerly, a customer would be entitled to a refund if the network upgrade costs estimate increased by more than 25% between the system impact study and the facilities study). FERC also ordered MISO to propose, in a compliance filing, additional provisions allowing refunds in the event of significant changes to cumulative network upgrade costs over the entire DPP process (not just between two phases).
- Changes to the provisions requiring restudies for customers with executed GIAs. FERC accepted MISO’s proposal whereby, instead of conducting restudies (as it had previously done) upon a withdrawal of a higher-queued project, MISO will simply determine if any common use or shared network upgrades are still needed and if so, reallocate the upgrade costs “among the remaining projects that require the upgrade(s) in question.” FERC also ordered MISO to clarify in a compliance filing what events (besides withdrawal of higher-queued projects) would trigger restudies.
The order was released on January 3, 2017 in Docket ER17-156-000.
Disclaimer
This blog is made available by Foley & Lardner LLP (“Foley” or “the Firm”) for informational purposes only. It is not meant to convey the Firm’s legal position on behalf of any client, nor is it intended to convey specific legal advice. Any opinions expressed in this article do not necessarily reflect the views of Foley & Lardner LLP, its partners, or its clients. Accordingly, do not act upon this information without seeking counsel from a licensed attorney. This blog is not intended to create, and receipt of it does not constitute, an attorney-client relationship. Communicating with Foley through this website by email, blog post, or otherwise, does not create an attorney-client relationship for any legal matter. Therefore, any communication or material you transmit to Foley through this blog, whether by email, blog post or any other manner, will not be treated as confidential or proprietary. The information on this blog is published “AS IS” and is not guaranteed to be complete, accurate, and or up-to-date. Foley makes no representations or warranties of any kind, express or implied, as to the operation or content of the site. Foley expressly disclaims all other guarantees, warranties, conditions and representations of any kind, either express or implied, whether arising under any statute, law, commercial use or otherwise, including implied warranties of merchantability, fitness for a particular purpose, title and non-infringement. In no event shall Foley or any of its partners, officers, employees, agents or affiliates be liable, directly or indirectly, under any theory of law (contract, tort, negligence or otherwise), to you or anyone else, for any claims, losses or damages, direct, indirect special, incidental, punitive or consequential, resulting from or occasioned by the creation, use of or reliance on this site (including information and other content) or any third party websites or the information, resources or material accessed through any such websites. In some jurisdictions, the contents of this blog may be considered Attorney Advertising. If applicable, please note that prior results do not guarantee a similar outcome. Photographs are for dramatization purposes only and may include models. Likenesses do not necessarily imply current client, partnership or employee status.
Author(s)
Related Insights
21 November 2024
Manufacturing Industry Advisor
MEMA Original Equipment Suppliers Annual Conference – Outlook Panel’s Economic and Growth Forecasts for the Automotive Industry
In a year of many global market challenges that have impacted the automotive industry, the MEMA Original Equipment Suppliers Annual Conference held on November 12 and 13 in Novi, Michigan presented a detailed analysis of the current situation and future outlook for the automotive industry.
21 November 2024
Health Care Law Today
Episode 35: Let’s Talk Compliance: Physician Compensation Plans and Trends of 2024
In this episode, Let’s Talk Compliance Hosts Jana Kolarik a partner of Foley’s Health Care Practice Group and PYA principal Angie Caldwell, discuss physician compensation plans and the latest trends in physician compensation of 2024.
21 November 2024
Manufacturing Industry Advisor
NHTSA Year In Review: What Will Drive NHTSA in 2025
Through 2024, the National Highway Traffic Safety Administration continued its efforts to improve safety statistics and reduce the number of annual fatalities.